Exploded View
Front Seat RemovalConnecting Rod Big End Side Clearance Inspection
Measure connecting rod big end side clearance.
Insert a thickness gauge [A] between the big end and either
crank web to determine clearance.
Connecting Rod Big End Side Clearance
Standard: 0.13 0.38 mm
(0.0051 0.0150 in.)
Service Limit: 0.58 mm (0.023 in.)
If the clearance exceeds ...
Air Intake Duct Assembly (Other than US, CA and CAL Models)
Install the seals [A] as shown in the figure.
Fit the projections [A] of the air intake valve to the hole [B]
of the air intake ducts.
Tighten:
Torque - Air Intake Duct Assembly Screws: 1.5 N·m (0.15
kgf·m, 13 in·lb)
Hang the shaft [A] to the air intake valve securely ...
Air Switching Valve
Air Switching Valve Operation Test
Refer to the Air Suction System Damage Inspection in the
Periodic Maintenance chapter.
Air Switching Valve Unit Test
Remove the air switching valve (see Air Switching Valve
Removal in the Engine Top End chapter).
Set the hand tester [A] to the × 1 ...